Accommodations SaaS Platform
Status report · Week ending 18 September 2026
Prepared by Priya Raman · 3 October 2026
Overall: Payment integration is three days behind and threatens the 6 August milestone.
Progress
46% complete
Forecast finish
12 January 2027
Budget
GBP 215k of GBP 500k spent against GBP 220k planned
Completed this period
- Multi-tenant data isolation completed and signed off
- Pricing and availability engine passed load testing at 4x expected volume
- Second developer onboarded to the billing codebase
Planned for next period
- Close out subscription billing integration
- Begin multi-currency and tax handling
- Agree the UAT entry criteria with the client
Milestones
| Core Module Complete | 24 Jun 2026 | Complete |
| Booking & Payment Modules Complete | 6 Aug 2026 | At risk |
| Development Complete | 16 Oct 2026 | On track |
| Go Live | 12 Jan 2027 | On track |
Risks and issues
- Payment provider sandbox access still pending — Fiona Gallagher, chasing daily
- Staging environment instability has cost two days this period — Infrastructure
Decisions needed
- Confirm whether multi-currency stays in scope for phase one — needed by 30 September
- Approve two weeks of contract QA capacity for UAT